How Long Does a Kitchen Remodel Take?

Realistic timelines from first call to final walkthrough — and what causes delays.

Get a Free Estimate

Get a Free Kitchen Design Consultation

Tell us about your kitchen — its size, what you want to change, and the best way to reach you. We will respond with next steps and a clear path to your written quote.

"How long will this take?" is one of the first questions every homeowner asks — and one of the hardest to answer honestly. A kitchen remodel is not one job. It is a chain of jobs, and each link depends on the one before it. This guide gives you realistic timelines so you can plan your life around the work.

Typical Timelines at a Glance

These are work timelines. The full process — from your first call to the final walkthrough — is longer, because design and material ordering happen before a single tool comes out. Plan on 3 to 6 months start to finish for a typical project.

Phase by Phase

1. Planning and design (2–6 weeks)

You define your goals, pick a layout, and choose materials. Rushing this phase causes the most expensive mistakes later. Good design takes time — and it is worth it. Our guide to 10 questions to ask before you remodel helps you start this phase right.

2. Ordering materials (4–12 weeks)

This is the hidden time-eater. Stock cabinets ship in 1 to 2 weeks. Semi-custom cabinets take 4 to 8 weeks. Fully custom cabinets can take 10 to 12 weeks or more. Appliances, specialty tile, and custom range hoods can also have long lead times. Smart contractors order everything before demo starts.

3. Demolition (2–5 days)

Old cabinets, countertops, and flooring come out. It is loud and dusty, but it is fast. This is also when hidden problems show up — water damage, old wiring, mold. Finding them now is actually good news, because fixing them later costs more.

4. Rough-in: electrical, plumbing, framing (1–3 weeks)

Walls get framed, wires get run, pipes get moved. Inspections from Charles County happen at this stage, and work pauses until each inspection passes. If your project needs permits, build inspection days into your expectations.

5. Drywall, paint, flooring (1–2 weeks)

Walls go back up, get finished and painted. Flooring usually goes in before cabinets in a full remodel.

6. Cabinet installation (3–7 days)

Cabinets go in and get leveled and secured. This is the moment your kitchen starts looking like a kitchen again.

7. Countertop template and install (1–3 weeks)

Here is a step most homeowners do not expect: stone countertops cannot be cut until the cabinets are in. A templater measures your exact cabinets, the slab gets cut at the shop (1 to 2 weeks), then it is installed. During this gap you have cabinets but no counters — and no working sink.

8. Backsplash, fixtures, appliances (1–2 weeks)

Tile goes up, the sink and faucet get set, lights get hung, and appliances slide into place.

9. Punch list and final walkthrough (a few days)

You and your contractor walk through together and list every small fix — a paint touch-up, a misaligned door, a missing outlet cover. Nothing is truly done until the punch list is done.

What Causes Delays (and How to Avoid Them)

Backordered materials. The number one delay. Avoid it by ordering everything before demo, and having a backup pick for key items.

Change orders. Changing your mind mid-project — moving an outlet, switching tile — ripples through the schedule. Finalize decisions during design.

Permit and inspection waits. County inspectors work on their schedule, not yours. A contractor who pulls permits early and schedules inspections ahead keeps this moving.

Hidden damage. Rot, mold, or outdated wiring found during demo. You cannot avoid what you cannot see — but your 10 to 20 percent budget contingency (see our cost guide) covers the money side, and a good contractor builds buffer days into the schedule.

Living Through It

For a mid-range or full remodel, expect 3 to 6 weeks without a working kitchen. Set up a temporary kitchen: microwave, toaster oven, coffee maker, paper plates, and a dishwashing station in the laundry room or bathroom. Plan for takeout and simple meals in your budget. Our what to expect guide covers daily life during the remodel in detail.

The Bottom Line

Work itself takes 4 to 8 weeks for most Waldorf kitchens, but the full journey from first call to final walkthrough is usually 3 to 6 months. The biggest schedule saver is ordering materials before demolition starts — and the biggest schedule killer is changing your mind mid-project.

Start Your Timeline

Thinking about a remodel this year? The sooner planning starts, the sooner materials get ordered. Tell us about your project through our short contact form and we will help you map out a realistic schedule for your kitchen.

Request your free estimate

Frequently Asked Questions

How long does a typical kitchen remodel take?

The construction work takes 4 to 8 weeks for most mid-range kitchens. A small refresh takes 1 to 3 weeks, and a full remodel with layout changes takes 8 to 14 weeks or more. The full process from first call to final walkthrough is usually 3 to 6 months including design and material ordering.

What part of a kitchen remodel takes the longest?

Material lead times are usually the longest part — custom cabinets can take 10 to 12 weeks to arrive. That is why good contractors order everything before demolition begins. During construction, the countertop template-to-install gap (1 to 3 weeks) often surprises homeowners.

Can I use my kitchen during the remodel?

During a small refresh, usually yes. During a mid-range or full remodel, expect 3 to 6 weeks without a working kitchen. Set up a temporary kitchen with a microwave, toaster oven, and coffee maker, and budget for takeout.

What delays a kitchen remodel the most?

Backordered materials are the top cause of delays, followed by mid-project change orders, permit and inspection waits, and hidden damage discovered during demolition. Finalizing all decisions before work starts prevents most delays.

When should I order cabinets and appliances?

Before demolition starts — ideally as soon as the design is final. Stock cabinets ship in 1 to 2 weeks, semi-custom in 4 to 8 weeks, and custom in 10 to 12 weeks or more. Ordering early is the single best way to keep your project on schedule.

✎ Request Free Estimate